Brief Introduction of Installation and Commissioning of Tofu Production Line

Brief Introduction of Installation and Commissioning of Tofu Production Line

1. Installation:

  1 Place the tofu production line in a clean and hygienic place with some distance from the wall, which is convenient for connecting tap water and drainage When connecting to the drainage ditch or sewer, the connection pipe from the machine to the drainage ditch should be ensured from high to low to prevent the normal discharge of the machine due to the accumulation of water in the pipe.

  2, power connection:

(1) Firmly fix the two-color wire to the ground;

(2) When using 380 volt power supply, connect the blue copper wire ({{2}} square) to zero, and the remaining three red copper wires (2. { {4}} Square) Connect three fire lines respectively;

(3) When using 220 volt power supply, connect the blue copper wire ({{2}} square) to the neutral wire, which is connected to three red copper wires ({{3} }. 5 square) connected to FireWire in a group.

0010010 nbsp; 0010010 nbsp; 3. Stabilize the tofu production line to prevent machine vibration from affecting the life of the machine.

Second, debugging:

  1. Remove the hopper on the electric grinder, loosen the anti-buckle of the electric grinder, and open the grinding cover to check whether the upper and lower grinding wheels are tight.

  2. Turn the filter holder by hand to see if the motor rotates flexibly. Put on the grinding cover and lock the buckle. When the handle of the electric grinder is "rough", loosen the handle on the grinding cover and move the filter. The rack can be rotated freely (the upper and lower grinding wheels are not in contact), and the hopper is restored.

  3 Connect the power supply, turn on the refining switch, start the electric grinder, turn on the water pipe and turn the high-end faucet on, let a small amount of tap water enter the electric grinder, and then slowly rotate the electric grinder in the direction of “fine” When the handle on the slag can be heard from the tap hole, you can turn off the switch.

  4 If the operation noise of the electric grinder is too loud, the diameter between the upper and lower grinding wheels and the feeder can be adjusted.

  5, press the heating switch, adjust the thermostat to 110 ℃, the heating indicator lights, turn off the thermostat, the heating indicator goes off, and complete the debugging.

  6 After the above work is completed, the tofu production line can make soy milk